Diablo Road Culvert Emergency Replacement
The Town of Danville will replace a drainage culvert on Diablo Road, east of Alameda Diablo. A full road closure, between Alameda Diablo and Avenida Nueva, will begin on March 23. The project is necessary to maintain safe travel on Diablo Road and integrity of the Town drainage system.
The full temporary road closure will result in the shortest project duration and cost efficiency. The project was expected to be completed April 13, but was extended to April 18 due to weather and supply issues.
The Town of Danville will replace a drainage culvert on Diablo Road, east of Alameda Diablo. A full road closure, between Alameda Diablo and Avenida Nueva, will begin on March 23. The project is necessary to maintain safe travel on Diablo Road and integrity of the Town drainage system.
The full temporary road closure will result in the shortest project duration and cost efficiency. The project was expected to be completed April 13, but was extended to April 18 due to weather and supply issues.
-
Diablo Road is Now Open
Share Diablo Road is Now Open on Facebook Share Diablo Road is Now Open on Twitter Share Diablo Road is Now Open on Linkedin Email Diablo Road is Now Open linkAs of Sunday, April 16, Diablo Road is re-opened. Town staff and contractors worked through the weekend to complete the Diablo Road Culvert Replacement Project through to paving. Some additional tasks will be scheduled in the coming weeks, including a guard rail on the westbound side of the road and road striping.
-
Diablo Road Will Re-Open April 18
Share Diablo Road Will Re-Open April 18 on Facebook Share Diablo Road Will Re-Open April 18 on Twitter Share Diablo Road Will Re-Open April 18 on Linkedin Email Diablo Road Will Re-Open April 18 linkImportant Project Update
The Town is pleased with how quickly the Diablo Culvert Replacement Project is coming along, although a few circumstances beyond our control have led to extending the completion date. At this point, we expect to re-open Diablo Road on Tuesday, April 18.Town engineering teams and contractor crews have been working diligently, and are near the finish line for this project. Unfortunately, both the wet weather and supply issues have hampered our progress. On Saturday alone, more than 1,000 tons of aggregate base (finely crushed rock) was delivered to the site – but not nearly as much as we had hoped – before the plant shut down. To mitigate supply issues as much as possible, crews have continued to work on other tasks within the project while we wait, to make sure that the delay is as short as possible.
These last days of the culvert project are filled with acquiring large quantities of supplies from multiple vendors, coordinating heavy equipment and precision engineering. This is a critical emergency replacement, and we appreciate the support the community has shown throughout. We will continue to provide updates on the project through Tuesday, and appreciate your patience while we make our roadways and drainage system better and safer.
-
Day 12 Update
Share Day 12 Update on Facebook Share Day 12 Update on Twitter Share Day 12 Update on Linkedin Email Day 12 Update linkOut with the old, in with the new! It’s day 12 of the Diablo Road Culvert Replacement project, and the 60-year-old culvert pipe has been removed. Crews excavated soil and rocks to get to the pipe, then removed it by sections. Contractors have been surveying the ground underneath to ensure the soil is prepped for the new pipe, and to make sure the placement will be perfect for drainage.While the rain last week was heavier than expected and did cause delays, crews hope to make up any time lost. This week, the new culvert pipe will be placed in sections, and crews will begin to pour concrete to set it in place. To subscribe to project updates, click the "Stay Informed" button. -
Day 5 Update
Share Day 5 Update on Facebook Share Day 5 Update on Twitter Share Day 5 Update on Linkedin Email Day 5 Update linkIt’s Day 5 of the Diablo Road Culvert Replacement project, and crews were busy over the weekend! In addition to continuing to build the replacement culvert pipe on-site, crews built a structure to pump water out of the project area, as well as divert water the culvert would normally handle. This is called a cofferdam, and will be especially helpful with this week’s anticipated rainfall, allowing the project to move forward as well as ensuring proper drainage. While we do expect rain this week, work is expected to continue and the cofferdam is expected to handle the rainfall successfully. For more information, view the project FAQ on this page.
-
March 23: Diablo Road Closure Begins
Share March 23: Diablo Road Closure Begins on Facebook Share March 23: Diablo Road Closure Begins on Twitter Share March 23: Diablo Road Closure Begins on Linkedin Email March 23: Diablo Road Closure Begins linkTomorrow is the big day! The Diablo Road Culvert Replacement project begins, along with the removal of several compromised eucalyptus trees. The culvert project is expected to end April 13, weather permitting, and the tree removal project may extend through the end of April.
Here are some tips to be prepared:
- Subscribe to updates: If you have not already, use the "Stay Informed" box on this page to subscribe to project updates.
- Review the detour map: We have developed a detour map that indicates closures and one-way traffic sections.
- Plan ahead for alternate routes: Leave a little early and have patience with your fellow drivers over the next three weeks.
While this project will present some obstacles in getting around Town, it will result in enhanced safety for our streets and drainage systems.
-
Detour Route Map Includes Concurrent Tree Removal Project
Share Detour Route Map Includes Concurrent Tree Removal Project on Facebook Share Detour Route Map Includes Concurrent Tree Removal Project on Twitter Share Detour Route Map Includes Concurrent Tree Removal Project on Linkedin Email Detour Route Map Includes Concurrent Tree Removal Project linkIn continuing efforts to make the Diablo Culvert Emergency Repair Project most efficient, the Town has scheduled removal of compromised eucalyptus trees over the same project period. As many in the community reported, more than 20 trees along Diablo Road near Alameda Diablo are prone to falling after recent storms. The Town is working with the private landowner to remove the trees, which will be done during the culvert replacement project window, March 23-April 13, weather permitting. During this time, Diablo Road between Fairway Drive and Alameda Diablo will be set up for one-way traffic only.
The Town has developed a detour route map with this area identified, as well as suggested alternate routes for eastbound and westbound travel to avoid the project area. Click here to download a PDF of the map for reference.
Please note that the Diablo Community Services District – not affiliated with the Town - intends to close the intersection of Avenida Nueva at Diablo Road. That closure is noted on the detour map and questions can be directed to: generalmanager@diablocsd.org
-
Outreach Update
Share Outreach Update on Facebook Share Outreach Update on Twitter Share Outreach Update on Linkedin Email Outreach Update linkAs the Town continues to prepare for the culvert replacement project, we are using multiple outreach methods to make sure the community has as much advance notice as possible for this urgent project. The final elements of the communications and outreach plan is being put in place this week, including:
- Deployment of 17 electronic and static advance warning signage at 13 locations, to the east and west of the project site
- Coordination Contra Costa County District 2 Supervisor’s Office, Contra Costa Public Works, San Ramon Valley Fire Protection District, San Ramon Valley Unified School District, TRAFFIX School Bus Service, and the Athenian School
- Direct communication with the Diablo Community Services District representatives, Mt. Diablo State Park representatives, Diablo Country Club, and St. Timothy’s Church
- Direct mail notification to 3,600+ residents that take access to and from the Diablo and Blackhawk Road corridor
- News Flash through the Danville Area Chamber of Commerce and
- Press release and updates on all Town platforms, which have been viewed by more than 9,800 followers.
Once the project begins, Diablo Road will be CLOSED TO THROUGH TRAFFIC and travelers are asked to take an alternative route. A detour route map will be posted this week.
The Town is looking forward to completing this project as soon as possible to head off any further deterioration of the culvert.
-
Town Will Replace Culvert Beneath Diablo Road
Share Town Will Replace Culvert Beneath Diablo Road on Facebook Share Town Will Replace Culvert Beneath Diablo Road on Twitter Share Town Will Replace Culvert Beneath Diablo Road on Linkedin Email Town Will Replace Culvert Beneath Diablo Road linkPortion of Diablo Road will close for critical drainage infrastructure replacement.
The Town of Danville will replace a drainage culvert on Diablo Road, which will be closed to through traffic from Alameda Diablo to Avenida Nueva beginning March 23. The replacement project is necessary to maintain safe travel on Diablo Road and integrity of the Town drainage system, as the existing culvert pipe is at the end of its 60-year lifespan.
Town engineers inspected the culvert pipe while making storm-related repairs to the roadside slope in January. They found the pipe to be flattening, causing slope erosion and a dip on the surface of Diablo Road. The approximately 21-day project will include trenching across Diablo Road, removal of the outdated culvert, fabrication of the new culvert on-site, and installation of the replacement. The project is being planned with efficiency of time and resources, and full closure of Diablo Road will result in the shortest project duration and most efficient replacement of the critical drainage infrastructure.
Town staff have identified the potential project duration of March 23 to April 13 to make best use of nearby school break schedules. Diablo Road is expected to be closed for the duration of the project, from east of Alameda Diablo to Alameda Nueva.
-
Town Council Appropriates Funding for Construction
Share Town Council Appropriates Funding for Construction on Facebook Share Town Council Appropriates Funding for Construction on Twitter Share Town Council Appropriates Funding for Construction on Linkedin Email Town Council Appropriates Funding for Construction linkThe Danville Town Council appropriated funds for a construction contract for the emergency replacement of the Diablo Road Culvert. During the February 21 Town Council meeting, staff presented background and plans for the project, including a public outreach plan. The Council authorized the emergency storm drain culvert replacement under the local emergency declared January 10.
Follow Project
Lifecycle
-
Emergency Permit Application
Diablo Road Culvert Emergency Replacement has finished this stageDanville submits emergency permit applications to regional regulatory agencies for the culvert repair.
-
Funding Appropriation
Diablo Road Culvert Emergency Replacement has finished this stageDanville Town Council appropriates funds for the project, awards a construction contract, and authorizes work to begin in late March.
-
Initial Public Notification
Diablo Road Culvert Emergency Replacement has finished this stageDirect mail notification to neighborhoods that access off of Diablo and Blackhawk Road, deployment of advance warning signage, and media releases.
-
Construction
Diablo Road Culvert Emergency Replacement is currently at this stageExpected to be March 23-April 13, weather permitting.
Fact Sheet- Diablo Road Culvert
Detour Route Map
Who's Listening
-
Salama
NPhone 925-314-3348 Email nsalama@danville.ca.gov