Day 5 Update
It’s Day 5 of the Diablo Road Culvert Replacement project, and crews were busy over the weekend! In addition to continuing to build the replacement culvert pipe on-site, crews built a structure to pump water out of the project area, as well as divert water the culvert would normally handle. This is called a cofferdam, and will be especially helpful with this week’s anticipated rainfall, allowing the project to move forward as well as ensuring proper drainage. While we do expect rain this week, work is expected to continue and the cofferdam is expected to handle the rainfall successfully. For more information, view the project FAQ on this page.