A development plan application has been submitted by Trumark Homes. The proposed subdivision includes the seven-acre Borel property located at 3020 Fostoria Way. The project includes 170 residential units. A total of 46 units would be for-rent apartments, and 124 units would be for-sale townhomes. All 46 units would be restricted to rent to qualifying low-income households. All the buildings would be three stories, with a maximum height of 40 feet.

Project Plans 09.29.23

Update October 26, 2023

The project was taken to the October 26 Design Review Board meeting for review and to provide preliminary feedback to the applicant on the proposed architectural and landscape design for the project. The project will return to the Design Review Board at a future date for formal review and action.

Update November 30, 2023

The project returned to the Design Review Board for formal review and approval. Trumark Homes has submitted a revised subdivision and development plan application for the seven-acre Borel property located at 3020 Fostoria Way. The project includes 170 residential units. A total of 46 units would be for-rent apartments, and 124 units would be for-sale townhomes. All 46 units would be restricted to rent to qualifying low-income households. All the buildings would be three stories, with a maximum height of 40 feet.

Update January 23, 2024

Following the Design Review Board meetings, the development project was considered by the Planning Commission on January 23, 2024. The Planning Commission approved the request to subdivide the seven-acre parcel to allow for a 167-unit multi-family development. The project will include 124 for-sale townhouse units and 43 for-rent apartment units, with conditional approvals.

Updated Project Plans 12.22.23

Update July 1, 2024

Trumark Homes has received approval of a demolition and grading permit and is expected to commence construction activities in July 2024. The initial phase will include removal of trees and rough grading. This will be followed by the installation of subdivision improvements such as water, sewer, drainage, and roadways. Building construction is expected to begin in spring 2025.

Share 3020 Fostoria Way (Borel Property) on Facebook Share 3020 Fostoria Way (Borel Property) on Twitter Share 3020 Fostoria Way (Borel Property) on Linkedin Email 3020 Fostoria Way (Borel Property) link
loader image
Didn't receive confirmation?
Seems like you are already registered, please provide the password. Forgot your password? Create a new one now.
Submitting your comment
Cancel
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>