Diablo Road Trail Project
History
For three decades, the Danville Townwide Trail Master Plan (adopted 1989) envisioned building a multi-purpose trail to close the gap between the existing Barbara Hale Trail and access to Mount Diablo State Park. This public trail segment is one of the most difficult to construct because it needed to traverse a creek and hilly terrain across the privately-owned Magee property.
The opportunity came with the approval of the 69-home Magee Preserve project, which dedicated 93% of the 410-acre ranch to public open space and trail development. A condition of the project’s approval required the developer to construct the eastern segment of the trail (located within the subdivision) and a dedicated public easement to the Town to construct the western segment.
Trail Alignment
While the eastern portion of the trail (to be constructed by the developer) would be relatively flat, the western portion – constructed by the Town – would encounter the most challenging conditions, which include creek crossings, steep slopes, and the most appropriate location to cross Diablo Road to connect to the existing Barbara Hale Trail. A summary of trail options are contained in this Project Digest.
Trail Funding
At the time of the Magee Preserve project approval, the Town had roughly 50% of the necessary funds to construct the project. By summer 2021, given its importance as a regional trail link, the Town was able to secure the remaining half of the funds and the project is now considered 100% funded.
History
For three decades, the Danville Townwide Trail Master Plan (adopted 1989) envisioned building a multi-purpose trail to close the gap between the existing Barbara Hale Trail and access to Mount Diablo State Park. This public trail segment is one of the most difficult to construct because it needed to traverse a creek and hilly terrain across the privately-owned Magee property.
The opportunity came with the approval of the 69-home Magee Preserve project, which dedicated 93% of the 410-acre ranch to public open space and trail development. A condition of the project’s approval required the developer to construct the eastern segment of the trail (located within the subdivision) and a dedicated public easement to the Town to construct the western segment.
Trail Alignment
While the eastern portion of the trail (to be constructed by the developer) would be relatively flat, the western portion – constructed by the Town – would encounter the most challenging conditions, which include creek crossings, steep slopes, and the most appropriate location to cross Diablo Road to connect to the existing Barbara Hale Trail. A summary of trail options are contained in this Project Digest.
Trail Funding
At the time of the Magee Preserve project approval, the Town had roughly 50% of the necessary funds to construct the project. By summer 2021, given its importance as a regional trail link, the Town was able to secure the remaining half of the funds and the project is now considered 100% funded.
-
Work Along Diablo Road Begins March 3
Share Work Along Diablo Road Begins March 3 on Facebook Share Work Along Diablo Road Begins March 3 on Twitter Share Work Along Diablo Road Begins March 3 on Linkedin Email Work Along Diablo Road Begins March 3 linkThe Town is preparing for construction of the Diablo Road Trail. As the construction plan is finalized, crews will begin clearing the project area. Beginning Monday, March 3, some trees will be removed along Diablo Road, which may cause traffic disruption along the Diablo Road corridor near the Diablo community, between Fairway Drive and Alameda Diablo (see map). The Diablo Road Trail Project is aimed at enhancing safety and access for pedestrians and cyclists, and tree removal to make way for the trail will impact daily traffic in the area for 1-3 weeks. I’d appreciate it if you could share this information with your community so they can plan for potential disruptions to their commute
Project Details:
- Project Name: Diablo Road Trail Project (C-055)
- Location: Diablo Road between Fairway Drive and Alameda Diablo, Town of Danville (see attached map)
- Start Date & Duration: Work is scheduled to begin Monday, March 3, 2025, and is expected to last 1–3 weeks. We anticipate completion by March 7, 2025, with a firm end date no later than March 20, 2025.
- Work Hours: Monday through Friday, 9:00 AM to 2:00 PM, to reduce interference with school bell schedules.
- Traffic Notification: Lighted message signs will be placed at two locations along Diablo Road starting one week prior to March 3 to alert drivers of the upcoming project and potential traffic changes.
- Traffic Impact: Expect occasional delays or lane adjustments during work hours. Only one lane is expected to be closed when necessary to minimize disruption.
We apologize for any inconvenience and thank you for your patience and cooperation as we work to improve the corridor. Our goal is to keep disruptions to school operations and daily routines as minimal as possible.
-
Environmental Assessment & Preliminary Design Update
Share Environmental Assessment & Preliminary Design Update on Facebook Share Environmental Assessment & Preliminary Design Update on Twitter Share Environmental Assessment & Preliminary Design Update on Linkedin Email Environmental Assessment & Preliminary Design Update linkThe environmental assessment and preliminary design phases of the Diablo Road Trail have been successfully completed. In spring 2023, the Town submitted applications for environmental permits to both state and regional regulatory agencies, including the California Department of Fish & Wildlife (CDFW) and Regional Water Quality Control Board (RWQCB).
Unfortunately, the winter storms of 2023 not only led to the collapse of the Diablo Road culvert but also led to considerable erosion of the creek embankment designated for the trail alignment. In fall 2023, CDFW issued the Town an extensive list of conditions for permit approval. Beyond significantly increasing the project’s scope and corresponding costs, the Town believes that these conditions appear to be disproportionate to the project’s limited environmental impact. Over the next several months the affected areas will be resurveyed, redesigned, and resubmitted to the regulatory agencies with a detailed response.
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends
-
Notice of Public Review Period and Intent to Adopt a Mitigated Negative Declaration of Environmental Significance
Share Notice of Public Review Period and Intent to Adopt a Mitigated Negative Declaration of Environmental Significance on Facebook Share Notice of Public Review Period and Intent to Adopt a Mitigated Negative Declaration of Environmental Significance on Twitter Share Notice of Public Review Period and Intent to Adopt a Mitigated Negative Declaration of Environmental Significance on Linkedin Email Notice of Public Review Period and Intent to Adopt a Mitigated Negative Declaration of Environmental Significance linkWith 100% of the project funding secured, the Diablo Road Trail is entering its final phase before construction commences. This phase involves an environmental assessment of the trail project, completing the final design, and securing permits from regional and federal regulatory agencies.
Diablo Road Trail Initial Study/Mitigated Negative Declaration
Appendix B - Biological Resources and Arborist Report
-
Summary of Diablo Road Trail – Segments and Alignment
Share Summary of Diablo Road Trail – Segments and Alignment on Facebook Share Summary of Diablo Road Trail – Segments and Alignment on Twitter Share Summary of Diablo Road Trail – Segments and Alignment on Linkedin Email Summary of Diablo Road Trail – Segments and Alignment linkWe’re often asked: who is building the trail, where will it go, and what will it look like?
The paved multi-purpose trail will be built partly by Davidon Homes (developer of the Magee Preserve project) and partly by the Town.
Davidon Homes is required, as a condition of the development project’s approval, to build the eastern segment, approximately 3,750 linear feet or 0.71 miles, extending from the project entrance at Jillian Way westward to the EBMUD access gate (shown as the dashed white line).
The Town will build the western segment on a dedicated public easement, extending westward from the EBMUD access gate to Fairway Drive. A new crossing system will connect the new trail to the existing Barbara Hale Trail that runs along the north side of Diablo Road west to Green Valley Road.
The design features of the trail include: 8-foot wide paved pathway with 2-foot gravel shoulders separated 4-5 feet from Diablo Road with a physical barrier.
This project is included in the Town’s Capital Improvement Program as project C-055. A total of $5.7 million has been reserved to fully fund the construction of the western segment.
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends
-
Project Update: Funding Secured and Roadway Crossing Design Underway
Share Project Update: Funding Secured and Roadway Crossing Design Underway on Facebook Share Project Update: Funding Secured and Roadway Crossing Design Underway on Twitter Share Project Update: Funding Secured and Roadway Crossing Design Underway on Linkedin Email Project Update: Funding Secured and Roadway Crossing Design Underway linkSubstantial progress has been made on the Diablo Road Trail Project over the past 5 months. In addition to securing 100% of the project funds, preliminary trail alignments and sections as well as many of the environmental assessments, have been completed.
The Town Council also authorized a professional services agreement on March 15, 2022, to design the trail crossing at Fairway Drive which would ultimately connect the existing Barbara Hale Trail along the north side of Diablo Road to the new Diablo Road Trail along the south side.
The Diablo Road Trail is a 30+ year vision to close the gap between the existing Barbara Haile Trail and access to Mount Diablo State Park. This public trail will be constructed in partnership with Davidon Homes. The Town will construct the trail crossing system at Fairway Drive and western trail segment (shown in blue) while Davidon Homes will construct the segment shown in green.
To view a map of the project area, click here.
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends
-
Project-Level Environmental Assessment Underway
Share Project-Level Environmental Assessment Underway on Facebook Share Project-Level Environmental Assessment Underway on Twitter Share Project-Level Environmental Assessment Underway on Linkedin Email Project-Level Environmental Assessment Underway linkCurrently, an environmental assessment – specific to the project scope – is underway. This part of the effort is expected to conclude in winter 2022. After its completion, the Town would be able to complete final design work and begin the work of securing approvals from regulatory agencies.
Follow Project
Project Timeline
-
Identify Needs, Adopt a Plan
Diablo Road Trail Project has finished this stageDanville Townwide Trail Master Plan, adopted in 1989, identified this trail gap between Barbara Hale Trail and Mt. Diablo State Park
-
Obtain Public Easement
Diablo Road Trail Project has finished this stageSecure a public easement through a condition of approval for the Magee Preserve project, which dedicated 93% of the 410-acre ranch to public open space and trail development.
-
Evaluate Trail Alignments
Diablo Road Trail Project has finished this stageDetermine the most accessible, least environmentally impactful, and least expensive trail alignment.
-
Secure Project Funding
Diablo Road Trail Project has finished this stageSeek grant funding sources to complete the project funding plan.
-
Environmental Assessment
Diablo Road Trail Project is currently at this stageProject-specific environmental analysis and regulatory permitting process underway. Anticipated completion end of Summer 2024.
-
Final Project Design
this is an upcoming stage for Diablo Road Trail Project -
Construction
this is an upcoming stage for Diablo Road Trail Project -
Project Complete
this is an upcoming stage for Diablo Road Trail Project
Who's Listening
-
Transportation Manager
Phone (925) 314-3374 Email ashields@danville.ca.gov
Document Library
-
Danville Townwide Trails Master Plan 1989 (excerpts).pdf (2.03 MB) (pdf)
-
Diablo Road Trail Project Digest October 2022.pdf (2.21 MB) (pdf)
-
Diablo Road Trail Project Digest October 2021.pdf (1.47 MB) (pdf)
-
Diablo Road Trail Xing Award of Contract.pdf (1.87 MB) (pdf)
-
Diablo Road Trail Crossing Map (203 KB) (pdf)
-
Diablo Road Trail - Project Digest March 2022.pdf (1.71 MB) (pdf)
-
Diablo Road Trail - Alignment Options.jpg (413 KB) (jpg)
-
Diablo Road Trail Feasibility Summary - Parks Commission.pdf (5.78 MB) (pdf)
-
Diablo Trail Notice of Intent and Public Review_20220930.pdf (104 KB) (pdf)
-
Diablo Road Trail Initial Study/Mitigated Negative Declaration_20220920.pdf (36.4 MB) (pdf)
-
Appendix A- Air Quality Data.pdf (559 KB) (pdf)
-
Appendix B- Biological Resources and Arborist Report.pdf (19.8 MB) (pdf)
-
Appendix C- Archaeological Survey Report.pdf (20.1 MB) (pdf)
-
Appendix D-Geohazarrds Study.pdf (3.9 MB) (pdf)