Share Diablo Road Trail Project on FacebookShare Diablo Road Trail Project on TwitterShare Diablo Road Trail Project on LinkedinEmail Diablo Road Trail Project link
History
For three decades, the Danville Townwide Trail Master Plan (adopted 1989) envisioned building a multi-purpose trail to close the gap between the existing Barbara Hale Trail and access to Mount Diablo State Park. This public trail segment is one of the most difficult to construct because it needed to traverse a creek and hilly terrain across the privately-owned Magee property.
The opportunity came with the approval of the 69-home Magee Preserve project, which dedicated 93% of the 410-acre ranch to public open space and trail development. A condition of the project’s approval required the developer to construct the eastern segment of the trail (located within the subdivision) and a dedicated public easement to the Town to construct the western segment.
Trail Alignment
While the eastern portion of the trail (to be constructed by the developer) would be relatively flat, the western portion – constructed by the Town – would encounter the most challenging conditions, which include creek crossings, steep slopes, and the most appropriate location to cross Diablo Road to connect to the existing Barbara Hale Trail. A summary of trail options are contained in this Project Digest.
Trail Funding
At the time of the Magee Preserve project approval, the Town had roughly 50% of the necessary funds to construct the project. By summer 2021, given its importance as a regional trail link, the Town was able to secure the remaining half of the funds and the project is now considered 100% funded.
History
For three decades, the Danville Townwide Trail Master Plan (adopted 1989) envisioned building a multi-purpose trail to close the gap between the existing Barbara Hale Trail and access to Mount Diablo State Park. This public trail segment is one of the most difficult to construct because it needed to traverse a creek and hilly terrain across the privately-owned Magee property.
The opportunity came with the approval of the 69-home Magee Preserve project, which dedicated 93% of the 410-acre ranch to public open space and trail development. A condition of the project’s approval required the developer to construct the eastern segment of the trail (located within the subdivision) and a dedicated public easement to the Town to construct the western segment.
Trail Alignment
While the eastern portion of the trail (to be constructed by the developer) would be relatively flat, the western portion – constructed by the Town – would encounter the most challenging conditions, which include creek crossings, steep slopes, and the most appropriate location to cross Diablo Road to connect to the existing Barbara Hale Trail. A summary of trail options are contained in this Project Digest.
Trail Funding
At the time of the Magee Preserve project approval, the Town had roughly 50% of the necessary funds to construct the project. By summer 2021, given its importance as a regional trail link, the Town was able to secure the remaining half of the funds and the project is now considered 100% funded.
Share Environmental Assessment & Preliminary Design Update on FacebookShare Environmental Assessment & Preliminary Design Update on TwitterShare Environmental Assessment & Preliminary Design Update on LinkedinEmail Environmental Assessment & Preliminary Design Update link
The environmental assessment and preliminary design phases of the Diablo Road Trail have been successfully completed. In spring 2023, the Town submitted applications for environmental permits to both state and regional regulatory agencies, including the California Department of Fish & Wildlife (CDFW) and Regional Water Quality Control Board (RWQCB).
Unfortunately, the winter storms of 2023 not only led to the collapse of the Diablo Road culvert but also led to considerable erosion of the creek embankment designated for the trail alignment. In fall 2023, CDFW issued the Town an extensive list of conditions for permit approval. Beyond significantly increasing the project’s scope and corresponding costs, the Town believes that these conditions appear to be disproportionate to the project’s limited environmental impact. Over the next several months the affected areas will be resurveyed, redesigned, and resubmitted to the regulatory agencies with a detailed response.
Share Notice of Public Review Period and Intent to Adopt a Mitigated Negative Declaration of Environmental Significance on FacebookShare Notice of Public Review Period and Intent to Adopt a Mitigated Negative Declaration of Environmental Significance on TwitterShare Notice of Public Review Period and Intent to Adopt a Mitigated Negative Declaration of Environmental Significance on LinkedinEmail Notice of Public Review Period and Intent to Adopt a Mitigated Negative Declaration of Environmental Significance link
With 100% of the project funding secured, the Diablo Road Trail is entering its final phase before construction commences. This phase involves an environmental assessment of the trail project, completing the final design, and securing permits from regional and federal regulatory agencies.
Share Summary of Diablo Road Trail – Segments and Alignment on FacebookShare Summary of Diablo Road Trail – Segments and Alignment on TwitterShare Summary of Diablo Road Trail – Segments and Alignment on LinkedinEmail Summary of Diablo Road Trail – Segments and Alignment link
We’re often asked: who is building the trail,where will it go, and what will it look like?
The paved multi-purposetrail will be built partly by Davidon Homes (developer of the Magee Preserve project) and partly by the Town.
Davidon Homes is required, as a condition of the development project’s approval, to build the eastern segment, approximately 3,750 linear feet or 0.71 miles, extending from the project entrance at Jillian Way westward to the EBMUD access gate (shown as the dashed white line).
The Town will build the western segment on a dedicated public easement, extending westward from the EBMUD access gate to Fairway Drive. A new crossing system will connect the new trail to the existing Barbara Hale Trail that runs along the north side of Diablo Road west to Green Valley Road.
The design features of the trail include: 8-foot wide paved pathway with 2-foot gravel shoulders separated 4-5 feet from Diablo Road with a physical barrier.
This project is included in the Town’s Capital Improvement Program as project C-055. A total of $5.7 million has been reserved to fully fund the construction of the western segment.
Share Project Update: Funding Secured and Roadway Crossing Design Underway on FacebookShare Project Update: Funding Secured and Roadway Crossing Design Underway on TwitterShare Project Update: Funding Secured and Roadway Crossing Design Underway on LinkedinEmail Project Update: Funding Secured and Roadway Crossing Design Underway link
Substantial progress has been made on the Diablo Road Trail Project over the past 5 months. In addition to securing 100% of the project funds, preliminary trail alignments and sections as well as many of the environmental assessments, have been completed.
The Town Council alsoauthorizeda professional services agreementon March 15, 2022, to design the trail crossing at Fairway Drive which would ultimately connect the existing Barbara Hale Trail along the north side of Diablo Road to the new Diablo Road Trail along the south side.
The Diablo Road Trail is a 30+ year vision to close the gap between the existing Barbara Haile Trail and access to Mount Diablo State Park. This public trail will be constructed in partnership with Davidon Homes. The Town will construct the trail crossing system at Fairway Drive and western trail segment (shown in blue) while Davidon Homes will construct the segment shown in green.
Share Project-Level Environmental Assessment Underway on FacebookShare Project-Level Environmental Assessment Underway on TwitterShare Project-Level Environmental Assessment Underway on LinkedinEmail Project-Level Environmental Assessment Underway link
Currently, an environmental assessment – specific to the project scope – is underway. This part of the effort is expected to conclude in winter 2022. After its completion, the Town would be able to complete final design work and begin the work of securing approvals from regulatory agencies.
Page last updated: 15 Dec 2024, 07:31 PM
Follow Project
Stay informed
Subscribe for project updates
Project Timeline
Identify Needs, Adopt a Plan
Diablo Road Trail Project has finished this stage
Danville Townwide Trail Master Plan, adopted in 1989, identified this trail gap between Barbara Hale Trail and Mt. Diablo State Park
Obtain Public Easement
Diablo Road Trail Project has finished this stage
Secure a public easement through a condition of approval for the Magee Preserve project, which dedicated 93% of the 410-acre ranch to public open space and trail development.
Evaluate Trail Alignments
Diablo Road Trail Project has finished this stage
Determine the most accessible, least environmentally impactful, and least expensive trail alignment.
Secure Project Funding
Diablo Road Trail Project has finished this stage
Seek grant funding sources to complete the project funding plan.
Environmental Assessment
Diablo Road Trail Project is currently at this stage
Project-specific environmental analysis and regulatory permitting process underway. Anticipated completion end of Summer 2024.
Final Project Design
this is an upcoming stage for Diablo Road Trail Project
Construction
this is an upcoming stage for Diablo Road Trail Project
Project Complete
this is an upcoming stage for Diablo Road Trail Project