The Community Presbyterian Church has submitted an application to allow the renovation and expansion of the existing church facility and for the construction of a new residential townhouse development. The church facility renovation and expansion includes a new 26,866 square foot youth/ministry building, a new 1035 square foot outdoor pavilion adjacent to the front entrance, expansion of the existing sanctuary and lobby totaling 2,507 square feet, renovation of other space within the existing building, a new soccer field and basketball court, and the construction of a new 68-unit Townhouse development, including 49 three-story townhomes with 19 accessory dwelling units (ADUs) incorporated into the townhomes.
Update May 22, 2026
On May 26, 2026, the project will be reviewed by the Planning Commission.
Planning Commission Agenda - May 26, 2026
Complete Transportation Impact Study
Complete Architectural Drawings
Update May 15, 2026
A public hearing notice was mailed to surrounding property owners within 750 feet of the site on May 14, 2026.
Update May 7, 2026
A public hearing has been set for Tuesday, May 26, 2026, at 5:00 p.m. at the Town Meeting Hall at 201 Front Street, Danville. A public hearing notice to all surrounding property owners within 750 feet of the site will be mailed at least ten days prior to the meeting.
The public hearing notice and Planning Commission meeting agenda will be posted here when they are finalized.
The applicant has requested, and the Town has found, that the application is exempt from the requirements of the California Environmental Quality Act (CEQA) based on the new California Law SB 130 which went into effect on July 1, 2025. This new law is applicable to infill housing developments.
The following final plans and documents have been submitted and will be presented at the planning commission meeting:
Project Architectural Drawings
Preliminary Stormwater Control Plan
Landscape and Relevant Drawings
Please note: while this traffic study had been prepared, the project is exempt from environmental review under State Law. The study does not make recommendation to improve traffic and circulation, which the Town will include as recommended conditions of approval for the project. However, because the project is exempt from the California Environmental Quality Act (CEQA), the adequacy of the study and/or its conclusions cannot be used as a legal basis for the Town's denial of the project.
Update April 16, 2026
On Thursday, April 16, 2026, the Design Review Board will provide second-round comments and review on the architecture and landscape plans for Community Presbyterian Church.
Update March 9, 2026
On Thursday, March 12, 2026, the Design Review Board will review and provide comments on the architecture and landscape plans for Community Presbyterian Church.
We are currently in the early stages of reviewing this application and have mailed a Request for Comments Letter to surrounding property owners and outside agencies. Comments and/or recommendations will be taken into consideration during our review and are requested prior to December 16, 2025 (see letter below).