Project Developer Submits Permit To Grade Project Site
The project developer has submitted a grading permit application for 600 Hartz Avenue. Grading preparation of the site will begin on March 5, 2023, including demolition of the remainder of the building and tree stumps, preparing the site, and mobilizing equipment. Excavation and grading are scheduled to start on March 15, 2023, and last approximately one month.
The off-haul route will turn left from the site onto Hartz Avenue to San Ramon Valley Boulevard. Trucks will be frequently entering and exiting the site -- and motorists, cyclists, and pedestrians should use caution when traveling through the area and be mindful of posted construction signage and traffic control personnel present at the site.